The Lockheed Martin F-35 Joint Strike Fighter program faces fresh challenges as the new year begins.
First, a long-awaited âshould costâ review from the U.S. Defense Acquisition Board might clarify whether Lockheed Martinâs continued optimism on the average procurement unit costs (APUC) is justified.
In addition, big cuts to the U.S. defense budget seem unlikely to spare the F-35, which is the Pentagonâs highest profile acquisition, and might undermine the basis for the APUC calculations.
Meanwhile, the ongoing debate over concurrency was further fueled by the leak last month of a Quick Look Review (QLR) of the programâs flight-test progress by Pentagon officials.
Although the QLR did not identify any fundamental design risks, it listed 13 causes for concern. Only two of these had been previously publicizedâthe problems with the Integrated Power Package and the Helmet-Mounted Display.
The QLR newly identified three more major problems: a fire risk with the fuel-dump subsystem, the tailhook of the F-35C and a âclassified survivability issueâ (presumably stealth-related). It also listed transonic buffet, maneuvering performance, fatigue life and test execution issues that might turn into major problems as development continues.
The report noted that âweight margins are extremely tightâ and cited a large volume of change requests and âlow design maturity.â It called for âserious reconsideration of procurement and production planning.â
Negotiations for the fifth low-rate initial production contract for 30 more jets continue. Lockheed Martin has agreed for the first time to share the costs of subsequently reworking them with changes mandated during development.
The program office has cut two aircraft from LRIP 5 to help pay for such concurrency costs, as well as 11 to 15 percent cost overruns on LRIPs 1 through 3. A similar number of aircraft are due to be built in LRIP 6. On January 5, Reuters reported that total U.S. procurement of F-35s from 2013 to 2017 (LRIPs 7 through 11) would be cut from 423 to about 300.
In another report last fall, the Pentagonâs director of operational test and evaluation (DOT&E) said he could not approve the start of initial pilot training in the six Lot 2 F-35As already delivered to Eglin AFB until more flight test hours had been accumulated on fully instrumented development and Lot 1 aircraft at Edwards AFB. The F-35 program office and the Air Force aeronautical systems commander disputed the DOT&Eâs risk assessment, but the aircraft nonetheless have not yet started flying.
Meanwhile, Lockheed Martin reported that it passed the planned total for 2011 of 872 F-35 flight tests by mid-November. The company suggested that this yearâs target of about 1,100 test flights could well be exceeded.